| Projects For sixteen years J. D. Hair &
Associates, Inc. (JDH&A) has been in the business of
providing horizontal directional drilling (HDD) expertise
to owners, contractors, and design firms. JDH&A has
been a key member of design teams for some of the most
significant and challenging HDD projects ever completed.
Some of these projects are described below.
Alliance Pipeline
Project
This high-pressure natural gas pipeline
extending 1,900 miles from northern British Columbia to
Chicago was designed and constructed to the highest
environmental and safety standards required by regulatory
bodies in both Canada and the United States. During the
initial feasibility and permitting stage, JDH&A reviewed
more than fifty major waterway crossings to determine the
optimum crossing installation method. This was followed by design and
construction monitoring for the HDD crossings in Canada
and design consultation for the HDD crossings in the
United States. All of the HDD crossings were completed by
the summer of 2000.
View
Photographs from the Alliance Pipeline Project
Colville River
Pipeline Project
This project consisted of four 4,300-foot HDD
installations through permafrost in the Alaskan Arctic.
Subsurface conditions tested the limits of HDD technology
while North Slope winter construction conditions required
work to be carried out on ice work pads in temperatures
ranging to -50 degrees Fahrenheit. JDH&A provided the
initial feasibility analysis that demonstrated to the
owner and permitting authorities that HDD could be
applied at the Colville River. This initial work was
followed by consultation relative to design and
construction methods and field engineering for quality
assurance. Construction began in early 1998 and all of
the crossings were completed by the spring of 1999. This project was
recognized in April of 2000 as one of five finalists for
the American Society of Civil Engineers Outstanding Civil
Engineering Achievement Award.
View
Photographs from the Colville River Crossing
Maritimes &
Northeast Pipeline Project
This pipeline, which brings Canadian gas into
the Boston Metropolitan area, is another Canadian-U.S.
system where JDH&A held the HDD position on a large
multidiscipline design team. JDH&A performed field
reconnaissance at more than 50 potential HDD crossing
sites in Maine, New Brunswick, and Nova Scotia to
evaluate HDD feasibility. This was followed by implementation of a
major geotechnical program for potential crossings in the
State of Maine, production of design drawings for
crossings in the U.S. and Canada, expert testimony before
regulatory agencies, and consultation during the
construction phase. All of the mainline crossings were
completed in 1999.
York County South
Carolina, Catawaba River Crossing
JDH&A provided design and consulting services
relative to the installation of a 24-inch diameter
sanitary sewer force main beneath the Catawaba River in
York County, South Carolina. In an effort to minimize
construction cost, this project was bid by both microtunneling
and horizontal directional drilling contractors. JDH&A's services included
preliminary feasibility analysis, HDD and microtunneling
designs, production of technical specifications, and
construction monitoring. Installation was completed in
the summer of 1996.
Vermont Gas
Systems, Missisquoi River Crossing
On this project JDH&A functioned as a consultant to
Vermont Gas Systems for the installation of a 16-inch
natural gas pipeline beneath the Missisquoi River.
JDH&A's services included preliminary design and
feasibility analysis, preparation of drawings and
specifications, and construction management. This 1,900 foot
crossing was the first horizontally directionally drilled
crossing in the state of Vermont. Preliminary engineering work began in 1990
with installation completed in the fall of 1995.
Pipeline Research
Committee at the American Gas Association
Under the sponsorship of the Pipeline Research
Committee at the American Gas Association, JDH&A produced
two manuals related to horizontally drilled pipeline
river crossings. The
first was an applications manual focused on drilling
fluids and their function in drilled crossings. The
second was an overall design guide covering engineering
considerations in evaluating, designing, and installing a
drilled river crossing. Work began in the fall of 1993
and both publications were completed by August of 1995.
Commonwealth
Electric Company, Cape Cod Canal Crossing
JDH&A provided total design and construction
management services involved with an 18-inch natural gas
pipeline crossing of the Cape Cod Canal. This involved
preliminary design and feasibility analysis, consultation
during the permitting phase, production of specifications
and design drawings, preparation of contract documents,
and construction management. This 1,400 foot crossing was the
first directionally drilled installation beneath the Cape
Cod Canal. Preliminary
engineering began in the fall of 1993 with installation
completed in the summer of 1995.
San Antonio, S. A.
Consulting and Operational Support
JDH&A provided consulting services relative to the purchase of a
horizontal drilling rig, drilling fluid system, and
downhole tooling for
San Antonio, S. A., an Argentine contractor located in
Buenos Aires. This support consisted of on-site
operational training with the equipment as well as
engineering support in the United States. Initial
consulting services began in 1993 with the first crossing
installation completed in the fall of 1994. Engineering
support is currently ongoing.
Sunshine Pipeline
Company, Proposed 30-inch Natural Gas Pipeline
JDH&A provided engineering services relative to
preliminary design and permitting of waterway crossings
on this proposed 30-inch natural gas pipeline extending
approximately 600 miles from Pascagoula, Mississippi to
Tampa, Florida. Evaluations were conducted at over 40
waterways to determine the optimum crossing method. Specific tasks undertaken
relative to the proposed drilled crossings on this
project included coordination of site surveys,
feasibility and route analysis, production of drawings
for permit applications, and production of plan &
profile drawings. Preliminary engineering work began in
late 1993. The project is currently on hold pending
market developments.
Central Hudson Gas
and Electric, Hudson River Crossing
On this project JDH&A functioned as design
consultant to Central Hudson for the installation of a 16-inch
natural gas pipeline beneath the Hudson River. This
involved preliminary design and feasibility analysis,
preparation of permit applications, geotechnical
investigation, preparation of specifications and design
drawings, and construction monitoring. The crossing,
located near Poughkeepsie, New York, was approximately 4,500
feet in length. The geology at the site required a
creative design involving a combination of cut and cover
and trenchless techniques. Installation was completed in
the spring of 1992. The crossing was recognized in 1993 as an
Outstanding Engineering Achievement by the New York State
Society of Professional Engineers.
Iroquois Gas
Transmission System
JDH&A functioned as a consultant to Iroquois Gas
Transmission for evaluation and design of drilled
segments on this 369 mile cross-country natural gas
transmission system extending from Iroquois, Ontario to
South Commack, New York. Detailed drilled crossing
designs and specifications were produced for the Hudson
River, Housatonic River, Milford Shoreline, and Northport
Shoreline crossings. Geologic conditions on all
crossings presented state of the art challenges. Because of this, JDH&A
recommended that the St. Lawrence River and Hudson River
be installed by cut and cover construction. The shoreline
crossings were installed by cut and cover construction at
the contractor's option. The Housatonic was installed by
horizontal directional drilling. JDH&A provided
support during contract negotiations and construction
monitoring assistance on this crossing. Installation was
completed by late 1991.
These projects represent
only a partial listing of JDH&A's experience. The
collective experience of the practice since its inception
in 1987 comprises over 50 miles of trenchless utility
construction with an estimated construction contract
value of well over 50 million dollars.
|